Traffic Lane Restrictions Planned For Decatur And Lake Mead Boulevard Intersection

 

Starting at approximately 9 p.m. Wednesday, Sept. 10 and continuing until 5 a.m. on Thursday, Sept. 11, traffic will be reduced to one travel lane in each direction through the intersection of Decatur and Lake Mead boulevards. The traffic disruptions during the overnight hours are necessary as crews continue sewer line installation work in the area.

A $2.9 million sanitary sewer rehabilitation project is underway by the city of Las Vegas. Work on the improvements started in June and will take approximately seven months to complete. Work is currently taking place on Coran Lane between Decatur Boulevard and Rancho Drive. The project also includes work on Rancho Drive between Vegas Drive and Coran, and on Vegas Drive between Rancho and Michael Way.

Insituform Technologies is the project contractor. The city of Las Vegas is funding the improvements. The entire project is slated for completion in early 2009.

Lane Restriction Map

-end

Return to News Release Index